, Special Report No 3/97 concerning the decentralized system for the implementation of the…

In forcesince 19 Mar 1997

2.10. On average, during the first half of 1994, the final versions of work programmes were not submitted by national authorizing officers until 34 days after the start of the implementation period. For the first six months of 1995 the situation improved, insofar as the work programmes were submitted, on average, seven days before the beginning of the period covered. However, this still represents a serious delay, bearing in mind the Commission requirement for PMUs to submit their work programmes 90 days before the start of the period covered, because the Commission needs the time to examine and approve the programmes.

2.11. The length of time required by the Commission for approval of the work programme is due to the cumbersome nature of the approval process itself (transit through Commission Delegation, central operational and financial services and approval by Financial Controller). During the first half of 1994, this process took 106 days on average. During the first half of 1995, the average time was reduced to 87 days, which was still excessive, as it meant that, on average, work programmes were not approved until the second half of the period covered by them.

2.12. A further important source of delays was the requirement that contracts with a value of more than 500 000 ECU must be submitted to the Commission in Brussels for endorsement at three different stages: firstly, the tender dossier and the shortlist of tenderers; then the evaluation report on the bids received; finally, the contract itself. The procedure leading up to the Commission's final endorsement took, on average, seven weeks from the date on which the contract was signed by the programme authorizing officer. On a number of occasions PMUs trimmed contracts in order to reduce the value to less than 500 000 ECU and thus avoid the need for approval by the Commission in Brussels.

Organization of the Commission departments (16)

The role of the Delegations

2.13. To a large extent the delays in approving work programmes and contracts were due to the involvement of the Commission in Brussels in the day-to-day running of the DIS, despite the provisions of the framework agreements concluded between the Commission and beneficiary countries, which emphasize the role of the Commission Delegations: