5.6. The role of staff at the Commission in Brussels should be focused on the development of policies and procedures and the monitoring and evaluation of programmes as a whole (see paragraph 2.21). The Commission should seek to restrict the number of programmes financed, as well as the number of projects and contracts within each programme, to a level at which its staff are better able to monitor them.
Programme management units
5.7. Although there was no provision for them at the outset of the PHARE programme, there has been a rapid proliferation of PMUs as the Commission did not seek to limit their numbers (see paragraph 3.4). The difficulties caused by devolution in favour of PMUs with limited experience may be seen as the result of a compromise which reduces the efficiency of implementation in the short term. In the medium term, however, national administrations' management skills should be reinforced through their participation in the PHARE programme (see paragraph 3.5).
5.8. The acquisition of management skills on the part of national administrations has been hampered by the marginalization of many PMUs (see paragraphs 3.6 - 3.7) and the budgetary constraints of beneficiary countries, which limit the possibilities of filling posts and recruiting quality staff on a long-term basis (see paragraph 3.8).
5.9. Western technical assistance has been the main instrument used by the Commission to support PMUs, but the effectiveness of the transfer of knowledge has been reduced, due to:
an ambiguous definition of the role of technical assistance (see paragraph 3.13);
the conditions governing the drafting of technical assistance reports (see paragraph 3.13);
the lack of ex post evaluation of the performance of technical-assistance measures (see paragraph 3.11);
a little-supervised system of extending technical-assistance contracts (see paragraph 3.12);
lack of experience and training among national staff of PMUs were obstacles to collaboration with western technical assistance (see paragraph 3.15).
5.10. The Commission has paid insufficient attention to developing alternative forms of backup support for PMUs. Its manual on decentralized procedures was only published and issued in 1994 and was not translated into the languages of the PHARE countries. Furthermore, the Commission provided only limited training in DIS procedures for the PMUs (see paragraphs 3.16 - 3.17).