, Special Report No 3/97 concerning the decentralized system for the implementation of the…

In forcesince 19 Mar 1997

2.7. When implementing the PHARE programme, the Commission paid insufficient attention to limiting the number of programmes, projects and contracts (14). Moreover, in each country, the PHARE funds were divided between too many ministries, with the result that financing was spread too thinly. The funds should be concentrated more on a limited number of programmes corresponding to clearly defined priorities and objectives. The various programmes are often implemented via numerous small projects, which in turn require a large number of contracts for their implementation. Whilst the conclusion of small contracts does allow small firms of consultants to compete on equal terms with larger firms, this must not be used as a pretext for the current dispersal of funds. Lastly, the relatively low threshold at which contracts become subject to compulsory tendering (50 000 ECU) (15) increases the administrative workloads of both PMUs and the Commission, with a resultant slowdown in the rate of implementation. Table 3 provides an overview of the number of programmes per year in the countries where DIS was the main channel for PHARE implementation (see paragraph 1.3).

>TABLE>

Delays in DIS procedures

2.8. Before any contracts are concluded under a sectoral programme, a programme authorizing officer (PAO) must be appointed, a PMU established and a work programme drawn up. The latter must be prepared by the PMU and accepted by the Commission in Brussels. The work programme system in fact ensures that the PMUs state clearly, in advance, how the funds will be used during the implementation period (usually six months). This procedure is a major guarantee of the sound financial management of the DIS, but, in practice, it has given rise to delays in both the submission of work programmes by the PMU and their subsequent approval by the Commission.

2.9. Analysis showed that the interval between the start of the programme (date of the Commission financing decision which makes it possible for the appropriations to be committed) and the Commission's approving the first advance was around one year (see Table 4).

>TABLE>