SPECIAL REPORT No 3/97 concerning the decentralized system for the implementation of the PHARE programme (period 1990 - 1995) together with the Commission's replies (submitted pursuant to Article 188C, paragraph 4, indent 2, of the EC Treaty) (97/C 175/02)
TABLE OF CONTENTS
Paragraphs Page
INTRODUCTION . 1.1 - 1.6 5
FUNCTIONING OF THE DECENTRALIZED MANAGEMENT SYSTEM . 2.1 - 2.22 7
Analysis of PHARE budget implementation rates . 2.1 - 2.3 7
Level of budgetary commitments . 2.1 - 2.3 7
Delays in implementing programmes . 2.4 - 2.12 7
Delays affecting the PHARE programme overall . 2.5 - 2.7 7
Delays in DIS procedures . 2.8 - 2.12 9
Organization of the Commission departments . 2.13 - 2.22 9
The role of the Delegations . 2.13 - 2.18 9
The role of the Commission in Brussels . 2.19 - 2.22 10
THE PROGRAMME MANAGEMENT UNITS (PMUs) . 3.1 - 3.34 11
The introduction of management units . 3.1 - 3.4 11
The role of the programme authorizing officer . 3.1 - 3.3 11
The growth of PMUs . 3.4 11
The role of the management units . 3.5 - 3.18 12
Main features of the management units . 3.5 - 3.9 13
The role of technical assistance to the management units . 3.10 - 3.15 14
Manual of DIS procedures . 3.16 - 3.18 14
Financial costs of the management units . 3.19 - 3.34 14
Management units' operating costs . 3.20 - 3.30 16
Cost of providing foreign technical assistance to management units . 3.31 - 3.34 17
THE TRANSPARENCY OF THE DECENTRALIZED MANAGEMENT SYSTEM . 4.1 - 4.35 17
Award of contracts . 4.2 - 4.10 20
Expenditure . 4.11 - 4.18 21
Revenue . 4.19 - 4.21 21
Accounting and financial reporting . 4.22 - 4.28 22
Reports on the effectiveness of measures . 4.29 - 4.35 23
CONCLUSION . 5.1 - 5.24 23
The operation of the DIS . 5.2 - 5.6 24
Programme management units . 5.7 - 5.15 25
Transparency of the DIS . 5.16 - 5.23 26
Overall conclusion . 5.24 26
ANNEXES 1 - 3 . 27-29
Replies of the Commission . 30
INTRODUCTION