1.6. In setting up a decentralized management system, the Commission set itself two major objectives: firstly, to put into practical form its determination to treat beneficiary countries as partners and to prepare them for their applications to join the European Union by involving their administrations in the management of PHARE funds; secondly, to increase the effectiveness of programme implementation: this would not have been possible under centralized procedures, because of the limited staff resources available at the Commission. In this context, the Commission must take account of the provisions of the Financial Regulation which stipulate that aid projects are to be implemented in close collaboration between the beneficiary and the Commission, and thus set a limit to decentralization, since the latter organization retains responsibility for the utilization of appropriations (13).
FUNCTIONING OF THE DECENTRALIZED MANAGEMENT SYSTEM
Analysis of PHARE budget implementation rates
Level of budgetary commitments
2.1. Table 2 summarizes the position for PHARE appropriations during the period 1990 - 1995.
>TABLE>
This table shows that the performance of the programme in financial terms cannot be judged only on the basis of the rate at which commitment appropriations are implemented, since the procedures for implementing the PHARE programme are such that, for any given project, there is normally a space of three to four years between the initial commitment and the project's completion.
2.2. The rate for contracts concluded in countries primarily using DIS was 59%, whereas the equivalent rate for countries where centralized procedures were widely used was higher (70%). As of 31 December 1995 a balance of 497 Mio ECU remained on PMU bank accounts: this figure represents around 38% of the funds channelled through decentralized procedures (1 294 Mio ECU for the period 1990-1995).
2.3. The payment figures published in the accounts thus do not give a true picture of the implementation of PHARE programmes because funds paid over by the Commission to the PMU by way of advances are treated as final expenditure. A similar situation may be observed in the accounting management of the EU's Structural Funds. Here, again, the payments relating to contracts subject to DIS procedures are slightly lower than those dealt with under centralized procedures (68% compared with 73%).
Delays in implementing programmes