2.4. Not all the factors which delayed implementation of the programmes were attributable to the DIS. In fact, the programme calls for close collaboration between the Commission and beneficiary countries and the responsibility for delays is very often equally divided.
Delays affecting the PHARE programme overall
2.5. When the PHARE programme was drawn up and its annual budgets established, the Commission's capacity to manage it was not taken into account. The PHARE programme was thus entered in Part B of the Commission's budget (operating expenditure), but the appropriations available under the budget for administrative costs did not cover the cost of the additional staff required for sound management. Nor was the PHARE programme established in terms of the absorptive capacity of the beneficiary countries. It was in fact observed that, after annual budgets had been committed, these countries were often slow to convert the sectoral framework programmes into concrete projects, whereas, under the demand-driven approach to the PHARE programme, the primary responsibility for the programme content rests with them. Lastly, national administrations had not always adopted a sectoral strategy, or had not completed legislative reforms prior to implementation of the programmes, despite the technical assistance made available to them.
2.6. Somewhat paradoxically, the 'efficiency` of committing budget appropriations throughout the year slowed down the implementation of certain programmes as a result, because the financing proposals (see Annex 2, Part A2) were prepared to excessively tight timetables (see paragraph 2.2). This resulted in programmes which were vague and thus delayed implementation of the projects. This was true of the 1994 indicative programme for Poland, which was not approved until mid-October 1994, which left barely three months in which to draw up the 15 financing proposals required for commitment of the 174 Mio ECU earmarked for the programme. When this happens, either considerable extra time is needed to finalize programmes after the funds have been committed, or the progress of operations is hampered as a result of over-hasty preparation.