, Special Report No 15/2000 on the Cohesion Fund, together with the Commission's replies

In forcesince 6 Jul 2000
96.

When the projects are closed the Commission and beneficiary Member States must, in accordance with Article 13 of the Regulation establishing the CF, evaluate the manner in which the projects have been carried out and must also evaluate the potential and real impact of their implementation in order to assess whether the initial objectives can be, or have been, achieved. The Commission has accordingly selected two external consultants on the basis of calls for tenders and these ex postevaluations of individual closed projects, numbering around 120 projects evenly distributed over the two sectoral domains in question, are to be carried out over a period of three years. The ex post evaluations that have already been completed are proving to be very useful, especially for improving the definition of the performance indicators in the two sectoral domains during implementation of the next CF generation.

Member States

97.

No Member State has yet completed the ex post evaluation of closed projects. Portugal has essentially drawn up a first account of jobs created, project by project, in 1997 and has begun an ex post evaluation process, while in Greece an evaluation of the management of projects and the quality of the work took place in 1995 to 1996.

98.

Although it is not a question of ex post evaluations, approximately 100 closed projects were examined in the cohesion countries, on the Commission's initiative, with the aim of evaluating their impact on the environment.

IMPACT OF THE COHESION FUND

Qualitative impact

99.

Analysis of the trends in the four cohesion countries shows encouraging results during the period (1994 to 1999) in transport infrastructure and in the environment, the fields of CF intervention where there has been notable progress towards reducing disparities relative to the rest of the Union.