, Special Report No 15/2000 on the Cohesion Fund, together with the Commission's replies

In forcesince 6 Jul 2000
61.

In Ireland, within the framework of a water-supply project in Limerick, expenditure totalling IEP 395324, 51 (approximately EUR 494155) incurred respectively before and after the period of eligibility from 1981 to 1992, was declared to the Commission as eligible expenditure.

62.

In Spain, recoverable VAT expenditure in connection with a water-supply project in Palma de Mallorca, amounting to approximately ESP 101 million (approximately EUR 0,6 million), was included in the total of expenditure eligible for CF financing. For another project in the Balearic Islands supplementary work totalling ESP 13,2 million (approximately EUR 77500) in connection with the inclusion of sand-removing equipment was added to the expenditure eligible for CF financing, although no provision had been made for it in the Commission's decision nor in any subsequent amendment submitted to the Commission by the Member State. The amount involved in this additional work had no repercussions on Community financing.

Finalisation of projects

63.

In Greece, the final technical report on a project in Argos stated that 72 km of old water mains had been replaced, whereas the on-the-spot check revealed a smaller quantity, i.e. 60 km. For another project involving a water pumping station the final report mentioned its completion, although on-the-spot checks revealed that it was neither completed nor operational.

64.

In Ireland, the results of the technical controls carried out by the units responsible were not checked against the statement of financial implementation. There was no systematic reconciliation to verify that the pattern of eligible expenditure was matched by corresponding progress in physical implementation.

65.

In Spain, in the case of a group of projects concerning reafforestation on the Balearic Islands, the eligible costs approved by the Commission in its decision of 28 July 1997(7) amounted to EUR 3,68 million, which is significantly below the EUR 10 million threshold mentioned in Article 10(3) of the CF regulation. In the case of another project concerning sewage treatment plants on the Balearic Islands, the on-the-spot audit revealed that the work was already well advanced at the time of the application for assistance dated 11 April 1995 and that two of the five plants entered had already been completed on the date of the Commission's approval of financing for them.