, Special Report No 15/2000 on the Cohesion Fund, together with the Commission's replies

In forcesince 6 Jul 2000
53.

Numerous amendments were found in several cases, and the projects concerned nevertheless achieved the same objectives as those initially approved. For a project at Argos in Greece, for example, the initial Commission decision made provision for a total cost of EUR 751000 for the laying of 20 km of water mains, i.e. an average cost per metre of EUR 38. A subsequent amendment to the initial decision introduced an additional investment of EUR 130000 for the construction of a reservoir and reduced the mains to 10 km, i.e. an average cost per metre of EUR 62; a third amendment to the decision increased the length of the mains to 72 km at a cost of EUR 993000, which took the average cost to EUR 14 and, finally, the cost of the investment made for the mains came to EUR 1377 000, which brought the average cost to EUR 19 per metre.

54.

At the monitoring level, the implementation reports on CF projects, which are attached to payment applications, usually provide very little information on the state of progress, the synergies or the aspect of coordination between these projects and other structural operations, even when this information is available in the Member States concerned.

55.

In respect of the approval of the final reports, which allows the final balance to be paid and the projects closed, there are also delays in the Commission departments but they are significantly shorter than those occurring in the initial phase of projects. The time between the submission of the final report and the related payment can be as much as approximately one year. The closure procedure sometimes produces several versions of the final implementation reports, as well as several successive applications for final payment, but the reasons for this are not immediately apparent from the case files.

Monitoring committees