However, this project approach was difficult to implement. At its launch projects were sometimes prepared in haste then, subsequently, in the course of implementation, allowance had to be made for an even distribution between the sectors. The fact that projects are submitted individually and at different times makes it difficult to compare them with each other and is not conducive to their selection for approval.
Within the framework of a multiannual budget, the Commission notifies the responsible national authorities of the indicative annual budget with a balanced distribution between transport infrastructure and the environment. The actions to be carried out are determined both on the basis of general guidelines as set out, in particular, in the Treaty, and on the basis of a national strategy with its own priorities in the two sectors concerned.
The programming for the two sectors concerned was, in general, carried out at different rates. Generally, the transport infrastructure sector can draw on long experience of programming and had sufficient well-designed projects, whereas in the environmental field the experience acquired is of more recent date. In most cohesion countries, therefore, the environmental projects were approved late in comparison with those in the field of transport infrastructure.
Generally, at national level, the project selection procedure takes into account how well-developed, in terms of quantity and quality, the project plans are, in particular how far advanced the projects are; it is also influenced by the chronological order in which projects for which assistance has been requested are submitted.
Even if the Regulation made no provision for any real programming for the CF with the goal of achieving a coherent overall view, in the medium term, of the actions to be implemented, its implementation on the part of the Commission, in partnership with the national authorities concerned, would have allowed the beneficiary Member States to improve the quality of the management of their applications for assistance in terms of impact and strategy.
Geographical distribution of the projects