Furthermore, the Commission should set up a procedure for the annual closure of projects and the cancellation of unexpended balances, as the Court has regularly recommended both in this and other fields (28).
GENERAL CONCLUSIONS
Considerations relating to the system of Protocols
The considerations produced by the Court on examining the implementation of the first two series of Protocols in its Special Report No 3/91, are still valid (29).
The right acquired by the recipient countries to the amounts set out in the Protocols for an unlimited period has meant that a smooth progression from one Protocol to the next has not been possible and that budgetary resources have been tied up which could have been used for other purposes. At the same time, the Commission found itself obliged to manage all four series of Protocols as from 1992. This situation will persist until the appropriations allocated to the various Protocols are exhausted and will run parallel to the management of the aid governed by the MEDA Regulation. In view of this situation, the Commission plans, on the basis of the Third and Fourth Protocols, annual payments of approximately 200 Mio ECU up to 1999, with payments of smaller amounts in the years following until the appropriations are exhausted (30).
The MEDA Regulation tackles the problem of the use of funds by adopting a procedure which can respond flexibly to the absorptive capacity of the recipient non-Member countries while respecting their priorities. In fact, the terms of this Regulation are such that the NMCs will no longer acquire a right to an amount from the budget but will negotiate a plan, the indicative nature of which is underlined, to run for a period of three years.
Considerations relating to the Commission's system of management
DG IB's management suffers from the inadequacy of its human resources, a lack of clarity in the division of tasks between the departments and of competences between the Commission's headquarters in Brussels and the Delegations. The powers of the Delegations should be increased to allow them to take, in good time, decisions which may prove necessary for the management of the projects. These increased powers should go hand in hand with the obligation to justify these decisions.