, Special Report No 1/98 in respect of bilateral financial and technical cooperation with…

In forcesince 29 Jan 1998
75.

In Morocco, the Agricultural Development Fund project (SEM/03/204/002) for which the Commission has paid, within the framework of the Third Protocols, 30 Mio ECU, was, according to the terms of the FA, to have been subjected to an audit by the Moroccan General Inspectorate of Finances for each of the three years of its implementation. The Delegation allowed this inspection to be replaced by an audit conducted by an external company which only partly covered the period of Community financing. This being the case, the correct use of 10 Mio ECU was not audited.

Authorisation of transfers between headings

76.

During the implementation of the training project in Morocco in the textile and leather industries (SEM/03/204/012), the Delegation agreed an increase of 37 % for the 'training network` component, which thereby increased from 1,09 Mio ECU to 1,5 Mio ECU.

77.

Transfers of appropriations between the budget headings of the FA were frequently approved. In the case of the «Rjim Maatoug» project (SEM/03/212/010), the changes observed also concerned the origin of the funds and the acceptance of the fact that the approved limits under certain headings were to be exceeded.

78.

Finally, in respect of the Helwan Waste Water project (SEM/03/220/005A) and, generally, all the infrastructure projects financed for the benefit of Egypt, the Delegation charged payments as long as appropriations remained available under the FA without concerning themselves with the specific amounts made available under each budgetary heading.

79.

These examples show that the managing departments too often tend to overlook the restrictions imposed by the amounts entered in the FA and only consider the overall budget. They are, however, largely unaware of the rules restricting expenditure to the appropriations allocated to each expenditure heading (26).