, Special Report No 1/98 in respect of bilateral financial and technical cooperation with…

In forcesince 29 Jan 1998
46.

The audits conducted showed that the most frequent causes of delays are the poor quality of the FAs and inadequate grasp of the public tendering procedures. One project involving loan operations for the benefit of small and medium-sized agricultural enterprises in Tunisia (SEM/03/212/015) thus began with a delay of two years due to the impreciseness of the FA in respect of the procedures for the release of funds, the rate of exchange to be applied when constituting the counterpart funds or even the provisions for intervention by the national accounting officer and the conditions regulating the use of bank accounts and the interest yielded. Two projects in Jordan also suffered such delays because of the time required by the Commission to conclude the technical assistance contracts in the case of the Economic geology project (SEM/03/628/013) and to acquire the laboratory equipment necessary for the implementation of the Cooperation project in science and technology (SEM/03/628/033A).

47.

These delays in the launch of the projects increased costs and sometimes affected results. Generally speaking, they resulted in a failure to meet the deadline for the implementation of the financial agreements for all 16 projects in the sample.

48.

In Morocco construction costs increased from 58,6 Mio ECU to a total of 64 Mio ECU for a project involving the improvement of the education system (SEM/03/204/006) and work initially planned for a project concerning the rehabilitation and protection of irrigated areas in the Ouarzazate and La Moulouya regions (SEM/03/204/013) could only be partially completed.

49.

In addition, within the framework of the implementation of the project for the development of training structures in the leather and textile industries in Morocco (SEM/03/204/012), 28 contracts for a cumulative total of 2,94 Mio ECU were not approved until after the deadline for the implementation of the financing agreement, which, in the absence of an additional clause to the FA extending this period, is irregular.

Financial management and monitoring of the projects

50.

The audits carried out have highlighted partial knowledge of the situation of the projects, weaknesses in the monitoring of the accounts of the paying agencies and financial management which is often inadequate.

Knowledge of the situation of the projects