Regulation (EU) 2017/1485
Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance. )
- 1Subject matter
- 2Scope
- 3Definitions
- 4Objectives and regulatory aspects
- 5Terms and conditions or methodologies of TSOs
- 6Approval of terms and conditions or methodologies of TSOs
- 7Amendments to the terms and conditions or methodologies of TSOs
- 8Publication of terms and conditions or methodologies on the internet
- 9Recovery of costs
- 10Stakeholder involvement
- 11Public consultation
- 12Confidentiality obligations
- 13Agreements with TSOs not bound by this Regulation
- 14Monitoring
- 15Annual report on operational security indicators
- 16Annual report on load-frequency control
- 17Annual report on regional coordination assessment
TITLE 1 OPERATIONAL SECURITY REQUIREMENTS
CHAPTER 1 System states, remedial actions and operational security limits
- 18Classification of system states
- 19Monitoring and determination of system states by TSOs
- 20Remedial actions in system operation
- 21Principles and criteria applicable to remedial actions
- 22Categories of remedial actions
- 23Preparation, activation and coordination of remedial actions
- 24Availability of TSO's means, tools and facilities
- 25Operational security limits
- 26Security plan for critical infrastructure protection
CHAPTER 2 Voltage control and reactive power management
CHAPTER 3 Short-circuit current management
CHAPTER 4 Power flow management
CHAPTER 5 Contingency analysis and handling
CHAPTER 1 General requirements on data exchange
CHAPTER 2 Data exchange between TSOs
CHAPTER 3 Data exchange between TSOs and DSOs within the TSO's control area
CHAPTER 5 Data exchange between TSOs, DSOs and distribution-connected power generating modules
CHAPTER 6 Data exchange between TSOs and demand facilities
CHAPTER 1 Roles and responsibilities
TITLE 1 DATA FOR OPERATIONAL SECURITY ANALYSIS IN OPERATIONAL PLANNING
- 64General provisions regarding individual and common grid models
- 65Year-ahead scenarios
- 66Year-ahead individual grid models
- 67Year-ahead common grid models
- 68Updates of year-ahead individual and common grid models
- 69Week-ahead individual and common grid models
- 70Methodology for building day-ahead and intraday common grid models
- 71Quality control for grid models
TITLE 2 OPERATIONAL SECURITY ANALYSIS
- 72Operational security analysis in operational planning
- 73Year-ahead up to and including week-ahead operational security analysis
- 74Day-ahead, intraday and close to real-time operational security analysis
- 75Methodology for coordinating operational security analysis
- 76Proposal for regional operational security coordination
- 77Organisation for regional operational security coordination
- 78Regional operational security coordination
- 79Common grid model building
- 80Regional outage coordination
- 81Regional adequacy assessment
CHAPTER 1 Outage coordination regions, relevant assets
- 82Outage coordination objective
- 83Regional coordination
- 84Methodology for assessing the relevance of assets for outage coordination
- 85Lists of relevant power generating modules and relevant demand facilities
- 86Update of the lists of relevant power generating modules and relevant demand facilities
- 87Lists of relevant grid elements
- 88Update of the list of relevant grid elements
- 89Appointment of outage planning agents
- 90Treatment of relevant assets located in a distribution system or in a closed distribution system
CHAPTER 2 Development and update of availability plans of relevant assets
- 91Variations to deadlines for the year-ahead outage coordination
- 92General provisions on availability plans
- 93Long-term indicative availability plans
- 94Provision of year-ahead availability plan proposals
- 95Year-ahead coordination of the availability status of relevant assets for which the outage planning agent i
- 96Year-ahead coordination of the availability status of relevant assets for which the outage planning agent i
- 97Provision of preliminary year-ahead availability plans
- 98Validation of year-ahead availability plans within outage coordination regions
- 99Final year-ahead availability plans
- 100Updates to the final year-ahead availability plans
CHAPTER 3 Execution of availability plans
TITLE 7 ENTSO FOR ELECTRICITY OPERATIONAL PLANNING DATA ENVIRONMENT
TITLE 1 OPERATIONAL AGREEMENTS
- 118Synchronous area operational agreements
- 119LFC block operational agreements
- 120LFC area operational agreement
- 121Monitoring area operational agreement
- 122Imbalance netting agreement
- 123Cross-border FRR activation agreement
- 124Cross-border RR activation agreement
- 125Sharing agreement
- 126Exchange agreement
- 127Frequency quality defining and target parameters
- 128FRCE target parameters
- 129Criteria application process
- 130Frequency quality evaluation data
- 131Frequency quality evaluation criteria
- 132Data collection and delivery process
- 133Synchronous area monitor
- 134LFC block monitor
- 135Information on load and generation behaviour
- 136Ramping period within the synchronous area
- 137Ramping restrictions for active power output
- 138Mitigation
TITLE 3 LOAD-FREQUENCY CONTROL STRUCTURE
- 139Basic structure
- 140Process activation structure
- 141Process responsibility structure
- 142Frequency containment process
- 143Frequency restoration process
- 144Reserve replacement process
- 145Automatic and manual frequency restoration process
- 146Imbalance netting process
- 147Cross-border FRR activation process
- 148Cross-border RR activation process
- 149General requirements for cross-border control processes
- 150TSO notification
- 151Infrastructure
TITLE 4 OPERATION OF LOAD-FREQUENCY CONTROL
TITLE 5 FREQUENCY CONTAINMENT RESERVES
TITLE 6 FREQUENCY RESTORATION RESERVES
TITLE 8 EXCHANGE AND SHARING OF RESERVES
CHAPTER 1 Exchange and sharing of reserves within a synchronous area
- 163Exchange of FCR within a synchronous area
- 164Sharing of FCR within a synchronous area
- 165General requirements for the exchange of FRR and RR within a synchronous area
- 166General requirements for sharing FRR and RR within a synchronous area
- 167Exchange of FRR within a synchronous area
- 168Sharing of FRR within a synchronous area
- 169Exchange of RR within a synchronous area
- 170Sharing of RR within a synchronous area
CHAPTER 2 Exchange and sharing of reserves between synchronous areas
- 171General requirements
- 172Frequency coupling between synchronous areas
- 173Exchange of FCR between synchronous areas
- 174Sharing of FCR between synchronous areas
- 175General requirements for sharing of FRR and RR between synchronous areas
- 176Exchange of FRR between synchronous areas
- 177Sharing of FRR between synchronous areas
- 178Exchange of RR between synchronous areas
- 179Sharing of RR between synchronous areas
CHAPTER 3 Cross-border activation process for FRR/RR
TITLE 10 COOPERATION WITH DSOS
TITLE 11 TRANSPARENCY OF INFORMATION
Source: EU legislation in force, consolidated versions and treaties (Cellar, Publications Office). Official publication. Reuse: Reuse authorised (Commission Decision 2011/833/EU).