Art. 5 Regulation (EU) 2017/1485

Terms and conditions or methodologies of TSOs

In forcesince 15 Mar 2021cited 5×
1.

TSOs shall develop the terms and conditions or methodologies required by this Regulation and submit them for approval to the Agency in accordance with Article 6(2), to the competent regulatory authorities in accordance with Article 6(3), or to the entity designated by the Member State in accordance with Article 6(4) and (5) within the respective deadlines set out in this Regulation. In exceptional circumstances, notably in cases where a deadline cannot be met due to circumstances external to the sphere of TSOs, the deadlines for terms and conditions or methodologies may be prolonged by the Agency in procedures pursuant to Article 6(2), jointly by all competent regulatory authorities in procedures pursuant to Article 6(3), and by the competent regulatory authority in procedures pursuant to Article 6(4) and (5).

2.

Where a proposal for terms and conditions or methodologies pursuant to this Regulation needs to be developed and agreed by more than one TSO, the participating TSOs shall closely cooperate. TSOs, with the assistance of the ENTSO for Electricity, shall regularly inform the regulatory authorities and the Agency about the progress of developing those terms and conditions or methodologies.

3.

Where TSOs deciding on proposals for terms and conditions or methodologies listed in Article 6(2) are not able to reach an agreement, they shall decide by qualified majority voting. A qualified majority for proposals in accordance with Article 6(2) shall require a majority of:

(a)

TSOs representing at least 55 % of the Member States; and

(b)

TSOs representing Member States comprising at least 65 % of the population of the Union.

4.

A blocking minority for decisions on proposals for terms and conditions or methodologies listed in Article 6(2) shall include TSOs representing at least four Member States, failing of which the qualified majority shall be deemed attained.

5.

Where TSOs deciding on proposals for terms and conditions or methodologies in accordance with Article 6(3) are not able to reach an agreement and where the regions concerned are composed of more than five Member States, they shall decide by qualified majority voting. A qualified majority for proposals in accordance with Article 6(3) shall require a majority of:

(a)

TSOs representing at least 72 % of the Member States concerned; and

(b)

TSOs representing Member States comprising at least 65 % of the population of the concerned region.

6.

A blocking minority for decisions on proposals for terms and conditions or methodologies listed in Article 6(3) shall include at least a minimum number of TSOs representing more than 35 % of the population of the participating Member States, plus TSOs representing at least one additional Member State concerned, failing of which the qualified majority shall be deemed attained.

7.

TSOs deciding on proposals for terms and conditions or methodologies in accordance with Article 6(3) in relation to regions composed of five Member States or less shall decide by consensus.

8.

For TSO decisions on proposals for terms and conditions or methodologies pursuant to paragraphs 3 and 5, one vote shall be attributed per Member State. If there is more than one TSO in the territory of a Member State, the Member State shall allocate the voting powers among the TSOs.

9.

Where TSOs fail to submit an initial or amended proposal for terms and conditions or methodologies to the regulatory authorities or to the Agency in accordance with Articles 6 and 7 or to the entities designated by the Member States in accordance with Article 6(4) within the deadlines set out in this Regulation, they shall provide the designated entity, competent regulatory authorities and the Agency with the relevant drafts of the terms and conditions or methodologies, and explain why an agreement has not been reached. The Agency, all competent regulatory authorities jointly, or the competent designated entity shall take the appropriate steps for the adoption of the required terms and conditions or methodologies in accordance with Article 6, for instance by requesting amendments or revising and completing the drafts pursuant to this paragraph, including where no drafts have been submitted, and approve them.

  • Regulation (EU) 2017/219515Law

    … com eles uma metodologia de atribuição dos custos resultantes das ações dos ORD nos termos do artigo 182.o, artigos 4.o e 5.o, do Regulamento (UE) 2017/1485. Essa metodologia deve proporcionar uma atribuição equitativa dos custos, …

  • Gesetz über die Elektrizitäts- und Gasversorgung56Law

    … Februar 2021, 2. Artikel 4 Absatz 2 und 3 der Verordnung (EU) 2016/1719 in der Fassung vom 22. Februar 2021, 3. Artikel 5 Absatz 8 der Verordnung (EU) 2017/1485 in der Fassung vom 22. Februar 2021, 4. Artikel 4 Absatz 6 der Verordnung (EU) …

  • Regulation (EU) 2021/2804Lawamends

    Články 5 až 8 nařízení (EU) 2017/1485 se nahrazují tímto: 1. Provozovatelé přenosových soustav vypracují podmínky nebo metodiky vyžadované tímto nařízením a předloží je v odpovídajících lhůtách stanovených v …

  • Systeemcode elektriciteitLaw

    … have approved an application from the TSO wishing to join the CGM process in accordance with the procedure set out in Article 5(3) of Regulation 2017/1485. 4. The TSOs referred to in paragraph 1 shall monitor that TSOs participating in the …

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 September 2024. Polskie sieci elektroenergetyczne S.A. v European Decision

    Pursuant to Article 5(1), Article 6(3)(b) and Article 76 of Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (OJ 2017 L 220, p. 1), the TSOs of each capacity …

    25 Sep 2024 · 62021TJ0483