Art. 4 Regulation (EU) 2017/1485

Objectives and regulatory aspects

In forcesince 2 Aug 2017cited 3×
1.

This Regulation aims at:

(a)

determining common operational security requirements and principles;

(b)

determining common interconnected system operational planning principles;

(c)

determining common load-frequency control processes and control structures;

(d)

ensuring the conditions for maintaining operational security throughout the Union;

(e)

ensuring the conditions for maintaining a frequency quality level of all synchronous areas throughout the Union;

(f)

promoting the coordination of system operation and operational planning;

(g)

ensuring and enhancing the transparency and reliability of information on transmission system operation;

(h)

contributing to the efficient operation and development of the electricity transmission system and electricity sector in the Union.

2.

When applying this Regulation, Member States, competent authorities, and system operators shall:

(a)

apply the principles of proportionality and non-discrimination;

(b)

ensure transparency;

(c)

apply the principle of optimisation between the highest overall efficiency and lowest total costs for all parties involved;

(d)

ensure TSOs make use of market-based mechanisms as far as possible, to ensure network security and stability;

(e)

respect the responsibility assigned to the relevant TSO in order to ensure system security, including as required by national legislation;

(f)

consult with relevant DSOs and take account of potential impacts on their system; and

(g)

take into consideration agreed European standards and technical specifications.

  • Regulation (EU) 2017/219515Law

    … com eles uma metodologia de atribuição dos custos resultantes das ações dos ORD nos termos do artigo 182.o, artigos 4.o e 5.o, do Regulamento (UE) 2017/1485. Essa metodologia deve proporcionar uma atribuição equitativa dos custos, …

  • Systeemcode elektriciteitLaw

    … Section). (14) The CGMM Proposal contributes to and does not in any way hamper the achievement of the objectives of Article 4(1) of Regulation 2017/1485. In particular, the CGMM Proposal serves the objective of determining common …

  • Judgment of the General Court (Third Chamber, Extended Composition) of 25 September 2024. Polskie sieci elektroenergetyczne S.A. v European Decision

    In the fourth plea, the applicant, supported by the Republic of Poland, submits that the contested ROSC methodology affects the ability of the TSOs to use the central dispatching model and, in particular, the integrated scheduling process …