PART III OPERATIONAL PLANNING
- 64General provisions regarding individual and common grid models
- 65Year-ahead scenarios
- 66Year-ahead individual grid models
- 67Year-ahead common grid models
- 68Updates of year-ahead individual and common grid models
- 69Week-ahead individual and common grid models
- 70Methodology for building day-ahead and intraday common grid models
- 71Quality control for grid models
- 72Operational security analysis in operational planning
- 73Year-ahead up to and including week-ahead operational security analysis
- 74Day-ahead, intraday and close to real-time operational security analysis
- 75Methodology for coordinating operational security analysis
- 76Proposal for regional operational security coordination
- 77Organisation for regional operational security coordination
- 78Regional operational security coordination
- 79Common grid model building
- 80Regional outage coordination
- 81Regional adequacy assessment
CHAPTER 1 Outage coordination regions, relevant assets
- 82Outage coordination objective
- 83Regional coordination
- 84Methodology for assessing the relevance of assets for outage coordination
- 85Lists of relevant power generating modules and relevant demand facilities
- 86Update of the lists of relevant power generating modules and relevant demand facilities
- 87Lists of relevant grid elements
- 88Update of the list of relevant grid elements
- 89Appointment of outage planning agents
- 90Treatment of relevant assets located in a distribution system or in a closed distribution system
CHAPTER 2 Development and update of availability plans of relevant assets
- 91Variations to deadlines for the year-ahead outage coordination
- 92General provisions on availability plans
- 93Long-term indicative availability plans
- 94Provision of year-ahead availability plan proposals
- 95Year-ahead coordination of the availability status of relevant assets for which the outage planning agent i
- 96Year-ahead coordination of the availability status of relevant assets for which the outage planning agent i
- 97Provision of preliminary year-ahead availability plans
- 98Validation of year-ahead availability plans within outage coordination regions
- 99Final year-ahead availability plans
- 100Updates to the final year-ahead availability plans
CHAPTER 3 Execution of availability plans
Source: EU legislation in force, consolidated versions and treaties (Cellar, Publications Office). Official publication. Reuse: Reuse authorised (Commission Decision 2011/833/EU).