Art. 101 Regulation (EU) 2017/1485

Management of the ‘testing’ status of relevant assets

In forcesince 2 Aug 2017
1.

The outage planning agent of a relevant asset the availability status of which has been declared as ‘testing’ shall provide the TSO, and, if connected to a distribution system, including closed distribution systems, the DSO or the CDSO within 1 month before the start of the ‘testing’ status, with:

(a)

a detailed test plan;

(b)

an indicative generation or consumption schedule if the concerned relevant asset is a relevant power generating module or a relevant demand facility; and

(c)

changes to the topology of the transmission system or distribution system if the concerned relevant asset is a relevant grid element.

2.

The outage planning agent shall update the information referred to in paragraph 1 as soon as it is subject to any change.

3.

The TSO of a relevant asset the availability status of which has been declared as ‘testing’ shall provide the information received in accordance with paragraph 1 to all other TSOs of its outage coordination region(s), upon their request.

4.

Where the relevant asset referred to in paragraph 1 is a relevant grid element interconnecting two or more control areas, the TSOs of the concerned control areas shall agree on the information to be provided pursuant to paragraph 1.