The outage planning agent of a relevant asset the availability status of which has been declared as ‘testing’ shall provide the TSO, and, if connected to a distribution system, including closed distribution systems, the DSO or the CDSO within 1 month before the start of the ‘testing’ status, with:
a detailed test plan;
an indicative generation or consumption schedule if the concerned relevant asset is a relevant power generating module or a relevant demand facility; and
changes to the topology of the transmission system or distribution system if the concerned relevant asset is a relevant grid element.
The outage planning agent shall update the information referred to in paragraph 1 as soon as it is subject to any change.
The TSO of a relevant asset the availability status of which has been declared as ‘testing’ shall provide the information received in accordance with paragraph 1 to all other TSOs of its outage coordination region(s), upon their request.
Where the relevant asset referred to in paragraph 1 is a relevant grid element interconnecting two or more control areas, the TSOs of the concerned control areas shall agree on the information to be provided pursuant to paragraph 1.