Each SGU which is a power generating facility owner of a type D power generating module connected to the transmission system shall provide the TSO with at least the following data:
general data of the power generating module, including installed capacity and primary energy source;
turbine and power generating facility data including time for cold and warm start;
data for short-circuit current calculation;
power generating facility transformer data;
FCR data of power generating modules offering or providing that service, in accordance with Article 154;
FRR data of power generating modules offering or providing that service, in accordance with Article 158;
RR data of power generating modules that offer or provide that service in accordance with Article 161;
data necessary for restoration of the transmission system;
data and models necessary for performing dynamic simulation;
protection data;
data necessary for determining the costs of remedial actions in accordance with Article 78(1)(b); where a TSO makes use of market based mechanisms in line with Article 4(2)(d), the provision of prices to be paid by the TSO shall be considered sufficient;
voltage and reactive power control capability.
Each SGU which is a power generating facility owner of a type B or a type C power generating module connected to the transmission system shall provide the TSO with at least the following data:
general data of the power generating module, including installed capacity and primary energy source;
data for short-circuit current calculation;
FCR data according to the definition and requirements of the Article 173 for power generating modules offering or providing that service;
FRR data for power generating modules that offer or provide that service;
RR data for power generating modules that offer or provide that service;
protection data;
reactive power control capability;
data necessary for determining the costs of remedial actions in accordance with Article 78(1)(b); where a TSO makes use of market based mechanisms in line with Article 4(2)(d), the provision of prices to be paid by the TSO shall be considered sufficient;
data necessary for performing dynamic stability assessment according to Article 38.
A TSO may request the power generating facility owner of a power generating module connected to the transmission system to provide further data where appropriate for operational security analysis in accordance with Title 2 of Part III.
Each HVDC system owner or interconnector owner shall provide the TSO with the following data regarding the HVDC system or interconnector:
nameplate data of the installation;
transformers data;
data on filters and filter banks;
reactive power compensation data;
active power control capability;
reactive power and voltage control capability;
active or reactive operational mode prioritization, if existing;
frequency response capability;
dynamic models for dynamic simulation;
protection data; and
fault-ride-through capability.
Each AC interconnector owner shall provide the TSO with at least the following data:
nameplate data of the installation;
electrical parameters;
associated protections.