Art. 182 Regulation (EU) 2017/1485

Reserve providing groups or units connected to the DSO grid

In forcesince 2 Aug 2017cited 4×
1.

TSOs and DSOs shall cooperate in order to facilitate and enable the delivery of active power reserves by reserve providing groups or reserve providing units located in the distribution systems.

2.

For the purposes of the prequalification processes for FCR in Article 155, FRR in Article 159 and RR in Article 162, each TSO shall develop and specify, in an agreement with its reserve connecting DSOs and intermediate DSOs, the terms of the exchange of information required for these prequalification processes for reserve providing units or groups located in the distribution systems and for the delivery of active power reserves. The prequalification processes for FCR in Article 155, FRR in Article 159 and RR in Article 162 shall specify the information to be provided by the potential reserve providing units or groups, which shall include:

(a)

voltage levels and connection points of the reserve providing units or groups;

(b)

the type of active power reserves;

(c)

the maximum reserve capacity provided by the reserve providing units or groups at each connection point; and

(d)

the maximum rate of change of active power for the reserve providing units or groups.

3.

The prequalification process shall rely on the agreed timeline and rules concerning information exchanges and the delivery of active power reserves between the TSO, the reserve connecting DSO and the intermediate DSOs. The prequalification process shall have a maximum duration of 3 months from the submission of a complete formal application by the reserve providing unit or group.

4.

During the prequalification of a reserve providing unit or group connected to its distribution system, each reserve connecting DSO and each intermediate DSO, in cooperation with the TSO, shall have the right to set limits to or exclude the delivery of active power reserves located in its distribution system, based on technical reasons such as the geographical location of the reserve providing units and reserve providing groups.

5.

Each reserve connecting DSO and each intermediate DSO shall have the right, in cooperation with the TSO, to set, before the activation of reserves, temporary limits to the delivery of active power reserves located in its distribution system. The respective TSOs shall agree with their reserve connecting DSOs and intermediate DSOs on the applicable procedures.

  • Regulation (EU) 2017/219515Law

    … разпределение на разходите, възникващи от действията на ОРС по член 182, параграфи 4 и 5 от Регламент (ЕС) 2017/1485. В тази методика трябва …

  • Directive (EU) 2019/94431Law

    … преносна система в съответствие с член 57 от Регламент (ЕС) 2019/943 и член 182 от Регламент 2017/1485 на Комисията [Регламент (ЕС) 2017/1485 на …

  • Loi du 9 juin 2023 modifiant : 1° la loi modifiée du 1er août 2007 relative à l’organisa…22Law

    … 2019/943 du Parlement européen et du Conseil du 5 juin 2019 sur le marché intérieur de l’électricité et à l’article 182 du règlement (UE) 2017/1485 de la Commission du 2 août 2017 établissant une ligne directrice sur la …

  • Commission Regulation (EU) 2017/2195 of 23 November 2017 establishing a guideline on ele…15Law

    … jointly elaborate a methodology for allocating costs resulting from actions of DSOs pursuant to paragraphs 4 and 5 of Article 182 of Regulation (EU) 2017/1485. The methodology shall provide for a fair allocation of costs taking into …