Implementation of the Envireg programme in Italy came up against particularly difficult problems connected with the implementation of the 1989-93 Italy CSF. In the case of Envireg the Court found a lack of programme monitoring, partly because financial data and progress reports had not been sent to the Commission, but also because the monitoring committees often met under somewhat precarious conditions (lack of precise data, representatives of regions were sometimes absent, minutes were not kept). As a result, only 3,5 % of the amounts transferred by the Commission by way of advances from 1991 (an amount of ± 3,1 Mio ECU (6 600 Mio LIT)) had been disbursed by the end of 1994. The problems of implementing the Italy CSF gave rise to a general agreement between Italy and the Commission, whereby the Envireg programme was extended until 31 December 1996 in the case of commitments and 31 December 1997 for payments.
In the Northern Ireland Envireg programme 96 % of the appropriations were earmarked for the reduction of pollution in coastal areas. 14 waste-water treatment projects were initially planned for that purpose. However the problems of bringing these projects into line with the water-quality directives, and the new Directive 91/271/EEC in particular, made it impossible for half of them to be carried out within the deadlines laid down in the programme. Seven projects were replaced by one large project for the renovation of one of the two Belfast treatment plants, serving 250 000 inhabitants. This project - for a total qualifying cost of ± 16,5 Mio ECU (13,3 Mio UKL), financed entirely out of national funds - had already started in 1986 and has absorbed 68 % of the ERDF contribution to this programme. It must be emphasised that the guidelines for the Envireg operational programmes (30) envisaged the financing of sewage plants for urban areas with a population of more than 100 000 only very exceptionally. Under these circumstances the objectives and priorities defined for Northern Ireland within the Envireg framework were only partially achieved, especially as regards the innovative nature of the projects.