, Special Report No 3/98 concerning the implementation by the Commission of EU policy and…

In forcesince 19 Mar 1998
87.

In Spain in the case of the 'Collector GLI-3 Valladares Lagares` project the cost increased by 26 % and the project was delayed for 28 months. For the Arteixo integrated pollution abatement project the deviation was 45 % from the initial cost and the project was delayed for 50 months. For the integral decontamination of Sada project the deviation was 47 % and the delay 15 months. For the integrated project for pollution abatement of Cabanas y Pontedeume - which was temporarily halted for 28 months for 'technical improvements` and is still under construction - the delays had already reached 38 months in February 1997 and its cost has increased by 23 %. For the integrated pollution abatement project at Ribeira, which is still under construction, the financial deviation is already 33,5 %. Finally, there is already a 30 % overrun on the cost of the Rianxo pollution abatement project, and the sewage treatment plant was not in operation in March 1996, although it had been completed a year earlier.

88.

A two-year delay was noted for the Coruña Ria underwater outfall project. Until November 1996 the project had not been officially accepted by the local authorities. In such cases the construction company has responsibility for the maintenance and operation of the plant. The high levels of rainfall and the absence of separate sewerage systems have resulted in a large part of the waste water being discharged untreated into the sea.

89.

In Greece, significant delays were found in all projects audited by the Court, for mainly technical and administrative reasons. The Rethymnon sewage treatment plant was delayed for 27 months and the cost has increased by 257 %. This project is still insufficient for the needs of the city. The construction of the sewage treatment plant at Veria had almost doubled in cost and at the time of the visit the project was still incomplete. The total cost for the two projects reached ± 6,1 Mio ECU.

90.

In Italy the project at Brienza started in July 1990 for a duration of 12 months. At the end of 1995 the project was not finished. The Taranto sewage project started in 1991, with a planned duration of one year, and was still not completed at the end of 1995.