In Spain the General Hydrological Plan for Galicia (PHGC) drafted by the regional authorities in 1990 included investments of ± 19,6 Mio ECU (3 125 Mio PTA) for the programme for pollution abatement in Ria de La Coruña. In 1994, the revised regional plan foresaw investments for the same programme of ± 39,2 Mio ECU (6 245 Mio PTA), which constitutes an increase of 100 % of the initial plan. Despite the fact that the various estimates are not really comparable, because particular factors must be taken into account (e.g. inflation, the inclusion of new projects and the requirements introduced by Directive 91/271/EEC), it must be said that a fair proportion of the increases in estimated cost are due to substantial delays in carrying out projects; delays produced by a variety of technical, legal (expropriations) and budgetary causes. Similar deviations from plan were observed in the 'Ria de Vigo` programme, which increased from ± 67,2 Mio ECU (10 700 Mio PTA) to ± 177,1 Mio ECU (28 200 Mio PTA) (163 %), and the 'Ria de Arousa` programme, which increased from ± 29,5 Mio ECU (4 697 Mio PTA) to ± 51,3 Mio ECU (8 167 Mio PTA) (73 %). The increases on the actual cost of the projects are examined in paragraph 86.
In Ireland, for the construction of the sewage plant in Dingle (OP Envireg), final expenditure was ± 6,1 Mio ECU (4,9 Mio IRL) compared to the planned ± 4,1 Mio ECU (3,3 Mio IRL), which is a 45 % increase over the planned costs.
In a French project, the planned cost for the construction of a small sewage station, financed by EAGGF Guidance (Société d'abattage des porcs ABERA) was 93 000 ECU (0,6 Mio FF). The final cost of the plant, after numerous technical improvements, reached ± 0,9 Mio ECU (6 Mio FF) or 10 times more than the estimated expenditure.