Finally, for the sewage plant of Meißen in Germany (ERDF OP Saxony) costs were 'corrected` upwards by engineers for supplementary works. These changes have nevertheless remained below the 10 % limit above which, according to national law [paragraph 2 (3.2) part B of the Verdingungsordnung Bauleistung (VOB-guidelines)], new prices would have had to be renegotiated. However, contrary to the view of the Commission, the Court considers that for the same project important savings could have been made without reducing the efficiency of the plant. In particular it is unnecessary and inappropriate to construct a cellar and a number of galleries under the entire plant, for the purpose of direct access to all pipes and basins (oxidation/nitrification basins, etc), via large and well-heated corridors. This is the only sewage works among those visited by the Court that incorporated such facilities.
The Court recognises the difficulty of implementing important infrastructure projects without cost increases. Price modifications are planned and accepted in all forms of short-term and long-term technical planning. Typically, increased costs do not directly result in increased Community support. However, significant changes in costs are a clear indication of weak planning and project management and of delays in carrying out the project. The delays result in most cases in increased costs.
Delays in carrying out projects and their effects on the increase of costs
There exists a strong correlation between the delays that were observed in the implementation of projects and increases in the construction costs.