Recital 66, Decision_act (EU) 2000/122

In forcesince 5 Jan 2000

The scale and complexity of the works and the essential link between the various stages are compounded by technical and operational difficulties which have delayed the full entry into service of the various piers and prevented the freeing-up of space for groundhandling equipment as previously planned. The full use of the space available, either by groundhandling equipment or by essential building materials, and the existing difficulties with regard to parking and traffic on the apron make it impossible to accommodate a new operator, whether a selfhandler or a service-provider, before the end of the period covered by the exemption,