Recital 59, Decision_act (EU) 2000/122

In forcesince 5 Jan 2000

The construction of the new apron to the west, which had originally been planned for the end of the year, would provide more than 14000 m2 for the parking of groundhandling equipment. However, the problems which have arisen in connection with the need to reorganise the drainage make the schedule for these works on the apron uncertain.

The plan of measures to overcome the constraints cited must be credible and unconditional, and be accompanied by a timetable for its implementation. The Commission cannot consider a plan whose implementation within the time allowed is uncertain to constitute a plan of appropriate measures within the meaning of Article 9 of the Directive.