Recital 40, Decision_act (EU) 2000/122

In forcesince 5 Jan 2000

In accordance with Article 9(4) of the Directive, the Commission has made a detailed analysis of the alleged space and capacity constraints, whether the decision taken is appropriate to those constraints, and the measures put forward to overcome them. Its examination drew upon the studies provided by the German authorities, its visit to Düsseldorf airport on 20 October 1999, and the technical assessment made at its request by Aerotec. Finally, the Commission took account of the comments made by the airport and the German Government concerning its analysis, and in particular those concerning space constraints due to the delay in the reorganisation of the terminal on account of the changes which had to be made to the working plan.

4.2. Examination of the constraints referred to by the German authorities

4.2.1. Background