The plan of appropriate measures presented in support of the first exemption also provided, in a second stage, for the creation of a new apron to the west. Half of the new apron, which is to be of a considerable size, will accommodate new aircraft positions, while the other half can be devoted to the storage of groundhandling equipment (on more than 14000 m2).
While the authorisation to build this apron extension does not in itself pose a problem, the scale of the works requires a major modification of the entire drainage system on the whole of the western part of the airport. This not only holds up the building works as such, it also requires authorisation from the authorities responsible for water protection, which in turn depends on the results of environmental tests. The time needed to perform these tests and to assemble the required documentation means that the authorisation is unlikely to be obtained before spring 2000.
4.3. Plan of appropriate measures