Recital 45, Decision_act (EU) 2000/122

In forcesince 5 Jan 2000

As stated above, the problems mentioned by the German authorities are the result of the fire of April 1996 and of the works in progress which, while forming part of a wider-ranging plan to extend the airport, are a direct result of that fire. These works do not extend the airport by simply adding new infrastructure or renovating an existing terminal, they primarily concern the almost total reconstruction of a building which was destroyed by fire. This brings with it quite specific constraints, due in particular to the need:

–

to first demolish the existing buildings, which in turn requires most of the existing infrastructure to be evacuated, before starting to rebuild (this is true in particular of pier B and the corresponding central part of the terminal building),

–

to proceed in stages (pier B and the adjacent part of the terminal building must be rebuilt before the central part of the terminal can be demolished) and combine demolition and building works on a single site,

–

carry out these works in the middle of an airport which must continue to operate.