As stated above, the problems mentioned by the German authorities are the result of the fire of April 1996 and of the works in progress which, while forming part of a wider-ranging plan to extend the airport, are a direct result of that fire. These works do not extend the airport by simply adding new infrastructure or renovating an existing terminal, they primarily concern the almost total reconstruction of a building which was destroyed by fire. This brings with it quite specific constraints, due in particular to the need:
to first demolish the existing buildings, which in turn requires most of the existing infrastructure to be evacuated, before starting to rebuild (this is true in particular of pier B and the corresponding central part of the terminal building),
to proceed in stages (pier B and the adjacent part of the terminal building must be rebuilt before the central part of the terminal can be demolished) and combine demolition and building works on a single site,
carry out these works in the middle of an airport which must continue to operate.