According to the German authorities, this unplanned reorganisation of pier A, at the request of the carriers, prevented the improvement in the situation forecast by the first Commission Decision. External circumstances and operational requirements resulted in a reduction of 500 m2 in equipment storage areas. Moreover, this reduction was accompanied by the closure of aircraft stand 80 and a reduction in the size of the adjacent stand.
2.2.2. Pier B