The comprehensive restructuring plan presented by the German authorities in support of the initial exemption request in 1998 provided for this infrastructure to come into operation in 2002, but was nevertheless supposed to allow the groundhandling market to be opened up at the beginning of 2001. The Commission Decision of 14 January 1998 forced the airport to open the market up early, as from 1 January 2000, on the grounds in particular of the space which should have been freed up when piers A and C were opened, the progress of work on pier B, and the new west apron.
Recital 16, Decision_act (EU) 2000/122
In forcesince 5 Jan 2000