Reconfiguration of the pier following the decision to adapt the "Airport 2000 plus" project to the changing needs of carriers and their passengers and in order to facilitate passenger transfer has involved an extension of the pier, and therefore of the building site. The Commission's assessment shows that:

–

the state of the works will not allow even part of the area currently occupied by the building site to be used to park groundhandling equipment by 1 January 2000, the date on which the current exemption expires, as foreseen by the Decision of 14 January 1998; the rebuilding of the pier has only just started, and it will not be possible to open the road junction to traffic for many months,

–

the buildings site has been kept as small as possible while ensuring safe conditions; apart from the roadway used by construction plant, there is only enough space to store a very small amount of building equipment,

–

the aircraft are separated from the building site only by the service road used by groundhandling equipment, and there is no room for any additional parking at this point.