KF as a wider project combines the following elements (see also figure 1 below):
The Baltic 1 and Baltic 2 farms, both located in German areas of the Baltic Sea. Baltic 1 was commissioned in 2011 and has a capacity of 48 MW. Baltic 2 was commissioned in 2015 and has a capacity of 288 MW.
The wind farm also called Kriegers Flak, located in Danish areas in the Baltic Sea. This wind farm of 600 MW capacity is planned for commissioning in 2022.
The grid connection from the German wind farms to the German shore, with a capacity of ca. 400 MW, using alternating current at 150 kV voltage over a distance of 136 km, commissioned in 2011 and 2015 respectively.
The grid connection from the Danish wind farm to the Danish shore (in the Denmark 2 bidding zone), with a capacity of 680 MW, using alternating current at 220 kV voltage over a distance of 77-80 km, commissioned in 2019.
A back-to-back converter station in Bentwisch, Germany, asynchronously connecting the Nordic and Continental synchronous areas.
Two high voltage alternating current cables linking the Kriegers Flak and Baltic 2 wind farms, with a capacity of 400 MW over a distance of 24,5 km.
To link the Kriegers Flak and Baltic 2 platforms, both offshore platforms had to be expanded.
A Master Controller for Interconnector Operation (‘MIO’). The MIO controls the load flow through the back-to-back converter station in real time, triggers countertrading in case a congestion occurs due to wind generation which is higher than estimated, triggers curtailment of the offshore wind farms where required as a last resort, and adapts set point values for voltage and reactive power at the back-to-back station to ensure voltage stability. It also forecasts, on an hourly basis, the remaining transmission capacity to be made available to the market.