71 5. ASSESSMENT › 5.2. Substantial problem for the operation of the system › 5.2.4. Legitimate expectations, Decision_act (EU) 2020/2123

In forcesince 11 Nov 2020

The reason that congestion management was mentioned as an essential part for the investment decision was that the investment decision had to take into account the interests of all involved parties. This included the role of the offshore wind facilities, which received subsidies via different national support systems. It is clear that if maximum capacity had to be granted for trade, this would result in an increased likelihood for the offshore wind facilities to be curtailed.