17 3. THE REQUESTED DEROGATIONS › 3.3. Network codes and guidelines, Decision_act (EU) 2020/2123

In forcesince 11 Nov 2020

The derogation request further sets out that the reservation of capacity in the long-term market shall be based on the capacity left over after deducting the installed wind power capacity. The reservation of capacity in the other market time units shall be based on the capacity left over after deduction of the forecasted wind power injection. While the request sets out that the curtailment of offshore wind farms (which is understood to refer only to the Baltic 1 and 2 and Kriegers Flak wind farms) caused by the reservation of cross-border capacity for cross-zonal trade shall be avoided in all market time units, the Commission understands this request to be the intended consequence of the other requested derogations and the described approach to capacity calculation and allocation, and not a request for separate derogations. In particular, the request expressly sets out that allocated capacity should be firm, thus no allocated transmission capacity shall be curtailed to prevent curtailment of the offshore wind farms.