Clearly describing the way the TSOs intended to resolve this conflict for the KF project, the presentations described that ‘capacity for wind power production to the onshore grid will be reserved based on the day-ahead forecast’ and that ‘the remaining capacity is to be given to the market coupling [thus defining the capacity available for trade] and used in the same way as the capacity on other interconnectors’. While the 2014 presentation did not highlight (in writing) the reduced capacity for the market compared to the earlier project plan, this was also not hidden. To the contrary, both presentations follow the exact same structure and, if held next to each other, clearly show the difference.
67 5. ASSESSMENT › 5.2. Substantial problem for the operation of the system › 5.2.4. Legitimate expectations, Decision_act (EU) 2020/2123