19 3. THE REQUESTED DEROGATIONS › 3.4. Duration of the requested derogation, Decision_act (EU) 2020/2123

In forcesince 11 Nov 2020

The Commission understands this to refer to the wind farms as they are currently already existing or, as regards Kriegers Flak wind farm, planned to be operational in the near future. Thus, for new wind farms, even as follow-on investments to the existing farms, their forecasted production would not be deducted from the total transmission capacity before calculating the residual capacity.