Thus, since 2010, the importance of the approach to congestion management was repeatedly set out in meetings with national regulators and the European Commission services, highlighting that different legal requirements from secondary legislation might be seen as in contradiction. At least the later presentations also clearly set out the planned approach the project parties intend to take to resolve this issue, and the impact this would have on cross-border capacity. During those years, national authorities and the Commission kept supporting the project, including with significant financial contributions, without requesting changes to the project structure.
68 5. ASSESSMENT › 5.2. Substantial problem for the operation of the system › 5.2.4. Legitimate expectations, Decision_act (EU) 2020/2123