96 5. ASSESSMENT › 5.5. Limitation of the derogation in time and conditions aiming to increase competition and integration with the internal market for electricity › 5.5.2. Other conditions, Decision_act (EU) 2020/2123

In forcesince 11 Nov 2020

As regards further conditions to be imposed, imposing an increase in the minimum capacity available for trade on an otherwise unchanged project would directly contribute to reinstating the problem to be resolved by the derogation in those hours where cables in the KF system are congested. On the other hand, where such cables are not congested, the maximisation principle applies in any case, thus the maximum technically feasible capacity already needs to be made available, up to the total transmission capacity of the transmission system.