101 5. ASSESSMENT › 5.5. Limitation of the derogation in time and conditions aiming to increase competition and integration with the internal market for electricity › 5.5.3. Procedure for eventual prolongation requests, Decision_act (EU) 2020/2123

In forcesince 11 Nov 2020

Whenever deciding on a prolongation request, the Commission shall take due account of the economic interests of the connected wind farms and involved system operators, but also of the wider socioeconomic impact of the derogation at a regional and European level. In particular, the review shall establish whether and how the KF system should be integrated into a wider regulatory framework for hybrid assets.