Germany replied to the remarks of the French Government by a fax message to the Commission dated 15 October 1993 stressing again its position concerning the applicability of Article 92 (2) (c) and 92 (3) (a).

VI

As explained when the Article 93 (2) procedure was initiated, Volkswagen's investment plans in the new Laender originate in its decision to accommodate the additional demand for cars in Eastern Germany and Eastern Europe after the political and economic changes in the region by starting production within this new market itself.

The investment is taking place in several stages. The first stage was the formation in December 1990 of a joint venture with THA, SAB, in which Volkswagen's stake is 12,5 %, although Volkswagen is responsible for its day-to-day management. The joint venture started small-scale assembly of the VW Polo (on a semi knocked-down (SKD) basis) at the existing former Trabant plant at Mosel (Mosel I) in May 1990, and began in 1991 to produce the VW Golf (on a CKD basis). A second phase, originally planned for 1994, involves the building of a new plant in Mosel (Mosel II) under the sole responsibility of Volkswagen Sachsen (VWS), a fully-owned subsidiary of Volkswagen created in December 1990. VWS also took over from Automobilwerke Eisenach cylinder head production in Eisenach in mid-1991, for which it will rent a modern building on the Eisenach-West site until the end of 1996. On 1 January 1992 VWS took over MWC, the owner of an existing engine plant (Chemnitz I), from THA. At this location the second phase involves the construction of a new engine plant (Chemnitz II), also originally planned for 1994.

According to information obtained from Germany in the course of the Article 93 (2) procedure:

1.

the timetable for the entire investment project has been substantially revised since the procedure was opened. On 13 January 1993 Volkswagen decided to postpone a large part of the investment relating to the new plants. As a result, the new car plant Mosel II, which had originally been scheduled for 1994, will not become fully operational until 1997. The new engine plant Chemnitz II, also originally planned for 1994, will start production in 1996;