First, to calculate the direct damage, the Municipality assumed that it would have taken SJB at least 2 years to sell 70 % of the housing units during the crisis period and start the construction works in the absence of the Supplementary Agreement. The Municipality budgeted the direct damage of a further 2-year delay at EUR 2,85 million for the PPP of which 50 % would be borne by the Municipality. Furthermore, it estimated an extra direct cost of EUR 50000 for the Municipality alone to maintain the deteriorated area (see Table 2).

Table 2

Direct damage calculated by the Dutch authorities

Direct damages during 2 years | PPP | municipality (50 %)

Interest cost over a credit facility (5 % during 2 years outstanding amount on 1.1.2009 EUR 17 million) | 1800000 | 900000

Temporary provision of fences, road signs and maintenance | 60000 | 30000

Provisions cost increase (indexation of 2,5 %) | 385000 | 192500

Extra planning costs i.e. costs related to the project office such as financial administration, insurance, etc. | 600000 | 300000

Maintenance deteriorated area | | 50000

Total | 2845000 | 1472500