The Commission notes in this regard the following. In the case at hand it is not contested, as stated in recital 30 above, that the construction works on the Damplein, which were initially planned to start in November 2005, were delayed since owing to several national court proceedings the necessary building permits could only be obtained in November 2008. In these circumstances SJB was no longer willing to implement the 2004 Cooperation agreement as initially agreed and, on the basis of contractual provisions, it requested the Municipality to renegotiate the initial arrangements.