In the Autumn of 2008, SJB made a proposal to the PPP to pay EUR 4 million for the land on the Damplein, instead of the EUR 7,2 million (value on 1 January 2003) originally agreed, whereby SJB would start the construction works in April 2009 regardless of whether the housing units had been pre-sold. In return for this decrease in price, SJB was therefore willing to waive its right to invoke the 70 % clause contained in the 2004 Cooperation Agreement and the damage suffered as a result of the delay of 3 years in delivering the building permits. SJB further proposed to contact an investor who would guarantee to buy the unsold housing units. According to the Dutch authorities this resulted in a price lower than that expected from a direct sale to private persons.