38 2. DESCRIPTION OF THE MEASURES › 2.3. THE RETROACTIVE PRICE DECREASE AND WAIVED FEES, Decision_act (EU) 2016/649

In forcesince 15 Jan 2016

The Supplementary Agreement also states that SJB started the construction works on the Damplein on 7 July 2009 and that it had to undertake those works without interruption. The works had to be finished by December 2011. In case of late delivery, SJB was to reimburse part of the decreased price. Delivery of the land would take place at the latest in mid-March 2010 and payment would take place at the latest on the day of delivery.