59 4. COMMENTS FROM THE NETHERLANDS › 4.3. COMMENTS REGARDING THE COMPATIBILITY OF THE STATE AID › 4.3.4. Proportionality, Decision_act (EU) 2016/649

In forcesince 15 Jan 2016

Furthermore, through its participation in the PPP, SJB will itself bear 50 % of the risks and the costs of the ground exploitation, thereby participating in the agreed decrease of the sales price. In order to arrive at break-even for the ground exploitation, it was decided that SJB should contribute EUR 2,6 million to the PPP (point 5.2.1 Ground Exploitation Masterplan Damcentrum) and, as the PPP bore 50 % of the costs of the school, 25 % of those costs is at the expense of SJB (EUR 0,7 million).