According to the 2004 Cooperation Agreement, the construction works would begin once the land had been made ready for construction (see recital 23 below) and the necessary building permits had been obtained. However, as regards the construction of the free sector housing units, the private developers were allowed to postpone construction until 70 % of these units, whether or not in combination with social housing units, in the sub-project area concerned had been pre-sold (Article 7.5 of the 2004 Cooperation Agreement, hereinafter: ‘the 70 % clause’). This 70 % clause is commonly found in construction contracts in the Netherlands and seeks to limit the risks for project developers of constructing real estate which might not be sold. The agreement did not, however, provide for any possibility to postpone construction as regards the commercial premises and the underground parking garage.
15 2. DESCRIPTION OF THE MEASURES › 2.2. THE REAL ESTATE PROJECT › 2.2.1. The construction phase, Decision_act (EU) 2016/649
In forcesince 15 Jan 2016