33 2. DESCRIPTION OF THE MEASURES › 2.3. THE RETROACTIVE PRICE DECREASE AND WAIVED FEES, Decision_act (EU) 2016/649

In forcesince 15 Jan 2016

In this regard SJB referred to the contractual provisions in the 2004 Cooperation agreement, in particular Article 6.6 of the 2004 Cooperation agreement which provides for the possibility of renegotiating the price and the delivery dates if the building permits were not delivered in time. According to SJB, since these permits were only delivered 3 years after the planned date, SJB could not be held to execute the Cooperation agreement unchanged. As a result the parties decided to renegotiate the initial arrangements.