31 2. DESCRIPTION OF THE MEASURES › 2.3. THE RETROACTIVE PRICE DECREASE AND WAIVED FEES, Decision_act (EU) 2016/649

In forcesince 15 Jan 2016

SJB started with the pre-sale of housing units in February 2007, but experienced difficulties selling these and eventually managed to pre-sell only 20 of the 67 planned units. Because of the delays encountered in obtaining the necessary building permits, these pre-sale contracts were annulled in September 2008 so that, when SJB finally obtained the permits to start construction works in November of that year, none of the housing units SJB was required to build on the Damplein had been pre-sold. In the meantime, the financial crisis had started and affected the Dutch real-estate market in particular.