, Special Report No 17/98 on support for renewable energy sources in the shared-cost actio…

In force

3.49. Eight out of 19 contractors had claimed budgeted instead of actual costs for labour and overhead rates. In general it is acceptable to apply budgeted rates during the course of the year, as long as these are adjusted to actual rates, once the financial year is closed and the actual rates are calculated. However, in most cases reviewed, the contractors did not intend to adjust their previous claims and in two cases they were either incapable or unwilling to calculate overhead rates based upon actual costs.

3.50. A fundamental problem was found to be the calculation and justification of the overhead rates charged under a full cost contract. For universities who have no cost-accounting system this problem is settled by the fact that their additional cost contracts have a fixed overhead rate set at 20 % of direct costs. All others have to calculate an actual rate. The model contract only gives limited and vague guidance as to which method to use and which costs are allowable or not allowable in the overhead rate. The audited contractors used overhead rates between 12 % and 210 % of personnel costs. Some contractors included costs in their overhead basis which were under the terms of the contract clearly ineligible, such as marketing costs, but many others were found to be very creative in including costs which were not specifically mentioned as non-eligible in the model contract, but which inflated the rates to an excessive level. Examples of these costs were non-project man-hours and depreciation costs for production equipment which is also used for RTD projects.

3.51. Two contractors had no system for recording time worked on projects at all. Another five had systems which fulfilled the conditions set by the contract, but were not fully reliable. One contractor had claimed an important number of man-hours which was performed outside of the eligible contract period, during the preparation of the project proposal.

3.52. Four contractors had unsatisfactory accounting systems, in which the allocation of cost elements to projects was not transparent and six contractors had claimed costs for which no justification existed or which were not directly related to the project.

3.53. In two cases the amounts claimed for travel included costs for trips to the United States of America for which no written prior approval from the Commission had been obtained.